Maintenance work on the Menai Suspension Bridge has been delayed again by another six months, contractors have confirmed.
The second phase of the works, which began in February 2025, was due to be completed by March this year, having already being postponed from August 2025, then December 2025, and then, April this year.
But UK Highways A55 Ltd says that has been postponed for a fifth time until next Autumn after water was found seeping into the steelwork on the underdeck.
The Deputy Minister for Transport, Mark Hooper, has described the latest delay as "unacceptable".
According to the contractors, the discovery had not been found during earlier inspections and the paint system it was planning to use could not be applied reliably.
But the company insisted a suitable solution had been found and they intend to reduce disruption by avoiding the use of traffic lights during peak hours.
Phase two was also affected by the hot summer weather with around 30 days of work lost.
Reacting to the news, Mark Hooper said: "People have put up with delays and inconvenience on this bridge for too long which is why this government has acted swiftly to get going on a third Menai crossing."
"I was extremely disappointed and frustrated to learn from the contractors that their programme of repairs, which has been beset by numerous delays, will be delayed once again."
"I have made it clear to UK Highways A55 Ltd since taking on this role the importance of maintaining momentum and providing confidence in the delivery programme, so this latest delay is unacceptable."
"I recognise that a project of this nature can encounter unforeseen challenges and that safety must remain paramount, but I need to fully understand what steps are being taken to address the underlying issues."
"I have written to the Chief Executive of Equitix, who are the governing body of UK Highways A55 Ltd, expressing my frustration and concerns and have called for an urgent meeting to discuss these matters to ensure completion by the revised date."
A Welsh Government spokesperson added: "The revised programme will continue to balance delivery of phase two with safe operation of the bridge and minimise disruption to local communities, including the removal of traffic management from the bridge for the rest of 2026."
The existing 7.5 tonne weight restriction will also remain in place while the works continue - last Friday afternoon, the bridge was closed for around an hour after it was used by an overweight vehicle.
In a writen statement to the Senedd, Mr Hooper warned the Welsh Government "made clear" that they expect the revised end date for the works to be met "and that no further avoidable slippage is acceptable".
He added: "I reiterate, these works sit alongside our wider commitment to improving resilience across the Menai Strait and those measures I announced last month."
"We are continuing to progress development work for a third Menai crossing and taking forward measures to improve the resilience of the Britannia Bridge."